WEBdeerSIGN image
    My Image

    ABOUT US

    My Image

    Trilogy Crossing Corp. The Company

    Trilogy Crossing 10 year anniversary

    Trilogy Crossing Corp. (TCC) is a full-service Engineering, Environmental, and Inspection company with expertise in bridge design, evaluation, and inspection within the oil/gas and forestry industries of Alberta and British Columbia.

    Trilogy Crossing Corp. was founded in 2012 on the principles of Integrity and Professionalism to achieve the highest levels of Environmental and Regulatory Compliance from project conception to construction completion and annual inspections.

    Trilogy Crossing Corp. brings together 3 disciplines into 1 complete stream crossing service. The 3 founding partners of Trilogy Crossing Corp. have in excess of 75 years combined bridge and road engineering, stream management compliance and pipeline crossing mitigation experience.

    SERVICES

    Engineering

    Environmental

    Inspection

    Drafting & Surveying

    OUR WORK

    Since 2012, Trilogy Crossing Corp. has been working with our clients to achieve their needs in regards to existing bridge inspection, new bridge designs, and site erosion mitigations. Below are just a few of the projects undertaken.

    Pumphouse Access bridge (Taylor B.C.) – March 2017

    Client: Spectra Energy Corp.
    Project type: New low-profile bridge design/construction

    My Image

    In the spring of 2017, construction started on the replacement of a “bridge” consisting of several beams that were not secured to another to maintain access to the River Water Pumphouse near Taylor B.C.. This structure was not built to any known standards or codes and not classified as a bridge to a professional, therefore it could not be given a load rating. The replacement bridge (12.192m or 40ft.) was manufactured as a low-profile one-piece structure to save on road height approach due to tight site constraints. The old sets of beams were removed, the substructure was re-set by compaction and placement of a spread mat foundation followed. This bridge was replaced quickly by transporting the completed bridge to site and lowering it in place where the old one was, leaving only a small amount of fill to be used for the bridge approaches due to its shallow beam depths. The project was completed successfully within a couple days and all construction documentation was recorded by Trilogy Crossing Corp.

    • My Image
    • My Image
    • My Image

    Mink Creek Crossing (Martin Hills A.B.) - December 2017

    Client: Spur Petroleum Ltd
    Project type: New permanent bridge design/construction

    mink creek crossing

    Construction started on a new bridge to be installed crossing Mink Creek near Slave Lake in northern Alberta in December of 2017. Trilogy Crossing Corp. created a plan and proposed bridge lengths and water clearances to develop a structure that was suitable for the new site. The new bridge is a 30.48m (100ft.) twin steel beam with timber modular deck structure, allowing the bridge to arrive in several pieces before final assembly on-site. Four piles were driven to refusal with a cap beam on each abutment and the bridge was set according to the plan prepared by Trilogy Crossing Corp. A post-construction assessment was completed once the bridge was in place and all methods were verified and documented for future reference.

    • My Image
    • My Image
    • My Image
    • My Image

    Holman Creek (Tommy Lakes B.C.) – December 2017

    Client: Canfor
    Project type: Temporary winter access bridge design/construction

    My Image

    In December of 2017 access was required to the other side of a large sized river for winter logging activities. Trilogy Crossing Corp. did a survey to create a bridge plan and determine the smallest bridge length required to span the frozen creek without impacting the water/ice. The solution was a set of 3 temporary spans (30.48m, 30.48m, 15.24m or in imperial 100ft., 100ft., and 50ft.) with each pier set on gravel bars in the river. One of the piers consisted of an arrangement of lock-blocks interlocked with one another set on mats below to distribute the heavy weight of logging trucks, and another consisted of a pre-assembled steel pier cap that could be lifted into position as once piece. These piers effectively took loaded logging truck loads from the bridge and distributed them into the ground around the ice. The bridge was successfully used for the duration of frozen conditions and disassembled before spring without impacting the creek.

    • My Image
    • My Image
    • My Image
    • My Image

    Nose Mountain A.B. Area – July 2018

    Client: Cenovus Energy Inc.
    Project type: Project type: New permanent bridge design/construction

    My Image

    During the summer of 2018, a client required the replacement of an 18.288m (60ft) bridge in poor condition. The bridge ballast walls were in very poor condition, letting fill through that would start to affect the stream quality if left unattended. A new 30.48m (100ft) bridge was installed in the same location to have adequate rock armoured embankment slopes to the creek and also to maintain the existing road alignment. The bridge was designed to withstand heavy loads (L100) that are required to access the area on the other side of the creek. Upon final completion, an as-built survey was completed to verify all components were installed according to the plans and all documentation was prepared to state the changes and final conditions of the structure.

    • My Image
    • My Image

    Bee Road (Nose Mtn, A.B.) – July 2018

    Client: Cenovus Energy Inc.
    Project type: Bridge substructure design/construction

    My Image

    The deteriorating condition of the ballast walls at the Bee Road bridge for a client required attention before failure. Since the bridge was set on “temporary” mats on each end of the bridge a more permanent fix was requested. The superstructure of the bridge (bridge beams) were in good condition, so the wooden deck components were replaced and the whole structure was re-used and set on a steel cap beam with steel bearing piles driven into the ground to refusal to achieve a permanent substructure condition. The new ballast wall was set with thick treated timber planks to promote longevity. This is a great example of taking an existing structure in good condition and retrofitting it to work for our client’s needs.

    • My Image
    • My Image
    • My Image

    Simonette Road 53km (Valleyview A.B.) – November 2018

    Client: Keyera Corp.
    Project type: New permanent 240’ 3-span bridge design/construction

    My Image

    In 2018, KEYERA CORP. required replacement of an old 70.635m long 4 span bridge over the Deep Valley Creek due to material deficiencies on the existing structure. Trilogy Crossing Corp. proposed a permanent 73.152m (240ft.) 3 span twin steel girder/concrete deck composite bridge to replace the existing bridge that requires access for heavy vehicle configurations to the nearby operating field. Many site constraints were present as the existing bridge had to remain open for traffic in the area, the bridge extents were to remain in the proper right-of-way, and proper fish habitat was to be maintained and monitored during the construction. Trilogy Crossing Corp. was involved in the construction of the bridge and prepared all quality assurance documentation for the project to ensure the bridge was constructed to the proper standards and codes used in the area.
    The structure was constructed in the fall of 2018 a few days ahead of schedule and open to traffic.

    • My Image
    • My Image
    • My Image
    • My Image
    • My Image
    • My Image
    • My Image

    Horseshoe Creek (Wonowon B.C.) – February 2019

    Client: Petronas Energy Canada Ltd.
    Project type: Temporary winter access bridge design/construction

    My Image

    An oil/gas client required access to the other side of a creek that did not freeze during winter conditions in order to do a reclamation project in the area. Trilogy Crossing Corp. proposed a plan and methodologies to cross the stream, and construction started in February 2019 and only took one two days to have the bridge in service. The bridge consisted of 2 temporary bridges (18.288m and 24.384m or in imperial 60ft. and 80ft.) that spanned the open water and had one pier on a dry gravel bar in the middle of the creek. The mats were positioned and the pier was built with interlocking lock-blocks to match the abutment elevations so the bridges were not on a slope. Due to the portable nature of the bridges, they were able to be installed in record timing. As-built documentation was prepared by Trilogy Crossing Corp. upon completion as required by regulation and the client successfully completed the reclamation project in a few weeks.

    • My Image
    • My Image
    • My Image
    • My Image

    Jackpine Road B.C. - January 2017

    Project type: Riprap/Bank Stabilization

    My Image
    • My Image
    • My Image
    • My Image
    • My Image
    • My Image

    Atick Creek B.C. area - December 2018

    Project type: Riprap/Bank Stabilization

    My Image
    • My Image
    • My Image
    • My Image
    • My Image
    • My Image
    • My Image
    • My Image

    Tupper B.C. area - January 2020

    Project type: Riprap/Bank Stabilization

    My Image
    • My Image
    • My Image
    • My Image
    • My Image

    Trilogy Crossing Corp. has been proud to collaborate with the following companies on the construction and mitigation projects completed to date for our clients:

    • 4Evergreen Resources LP.
    • Ruskin Construction Ltd.
    • Great Northern Bridgeworks
    • Mid-Knight Contractors Ltd.
    • Formula Contractors
    • Cornice Environmental Consulting Ltd.
    • Halfway River Ventures Ltd. (Arctic Construction Ltd.)

    CONTACT US

    • Alberta Office

      #315, 7326-10th St NE
      Calgary, AB

    • BC Office

      Moberly Lake Field Office

    OUR FAMILY

    Chad Dalke, President

    Rona Davies, VP Finance & Operations

    Brighid Dalke, Logistics Coordinator


    CERTIFICATIONS

    • ISN logo
    • trout logo
    • enform logo
    • comply works logo
    • apega logo